NT Hydro’s capital budget set to be cut by $62 million as projects delayed

The NT Hydro’s capital budget is set to be cut by more than $62 million, as delays have pushed completion on a number of major projects beyond 2021.

COVID-19, legal and regulatory delays and the ransomware attack in April 2020 — which prevented designers from accessing schematic drawings and getting plans approved — all caused project timelines to be pushed back, according to a letter sent to Infrastructure Minister Diane Archie by Noel Voykin, CEO of NT Hydro.

Design work and projects that were collaborations with NWT businesses were the only ones that made real progress in 2019, according to Voykin.

The $62 million cut more than halves the NT Hydro’s budget for capital project, while the Northwest Territories Power Corporation’s capital budget is also being cut by $44.4 million, around 46 per cent.

There are several big projects which have been delayed, which are contributing to the cuts.

The Inuvik High Point Wind Project remains behind schedule and will continue to be throughout the upcoming year, according to Voykin. The delays come as a result of difficulties navigating the regulatory applications for the winter access road. The timeline for passing the regulatory process could be further pushed back as the road now faces a legal challenge, according to Voykin.

Around $19.5 million of work was planned for this upcoming fiscal year and only $3.8 million is now forecast to be completed.

The ransomware attack in April 2020 meant NT Hydro had to pushback start dates on a number of projects, resulting in $34 million in cuts to the capital budget work that had been planned for 2020-21.

Projects delayed by the ransomware attack include the Snare Forks G2 Overhaul, delaying $16 million of work, the L-150 transmission line re-anchoring project, delays totalling $5.5 million, the Snare Falls substation refurbishment, where $1.9 million in work was planned and the new Sachs Harbour power plant, delaying around $3 million in work.

Legal difficulties have also delayed the NTPC’s purchase of the Hay River power grid. The power corporation is appealing to the Supreme Court that an independent arbitrator set too high a value for the town’s power services.

Bailey Moreton
Bailey Moreton
Bailey is new to the north, arriving from Ottawa where he studied journalism at Carleton University. He has worked for newspapers in Halifax, Windsor, and Ottawa. He came to the north hoping to see polar bears. He will settle for a bison. If you have a tip, send it to 905 252-9781, or [email protected].

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Minister Caroline Wawzonek speaks about Northern infrastructure investments

Caroline Wawzonek, Minister of Finance and Minister of Strategic Infrastructure, Energy and Supply Chains, has released a statement on the infrastructure investments in the North announced earlier this month.  

Hay River conducting public survey on impacts of climate change

The town of Hay River is conducting a public survey on the impacts of climate change as part of their Climate Adaption Plan. The plan will focus on how climate change is affecting people in town, what actions and priorities are identified as important and will gauge how concerned people are about it.

Investigators interviewing witnesses in Yellowknife after 35-year-old dies in custody

Saskatchewan RCMP report that they are currently interviewing witnesses and collecting evidence after a 35-year-old man from Nunavut was found dead less than three hours after being taken into custody on Thursday. A team from Sask. has been deployed to Yellowknife to conduct the investigation as an independent agency.

Freezing of chambers at Yellowknife’s Giant Mine to begin this summer

The Giant Mine remediation project team says thermosyphons are going to be installed at the underground chambers this summer. Currently, 237,000 tons of arsenic remain stored in the chambers on site. Crews are finishing internal work inside the new water treatment plant at Giant Mine. Commissioning activities are scheduled to start later this year and full operation of the new water is scheduled to begin in 2027.

Housing NWT completes hybrid housing project in Délı̨nę

Housing NWT has completed a hybrid housing project, bringing two new duplexes to Délı̨nę, bringing four new social housing spaces to the community. Their hope is that this hybrid construction pilot project can help pioneer new approaches to expanding housing in Northern communities.