NT Hydro’s capital budget set to be cut by $62 million as projects delayed

The NT Hydro’s capital budget is set to be cut by more than $62 million, as delays have pushed completion on a number of major projects beyond 2021.

COVID-19, legal and regulatory delays and the ransomware attack in April 2020 — which prevented designers from accessing schematic drawings and getting plans approved — all caused project timelines to be pushed back, according to a letter sent to Infrastructure Minister Diane Archie by Noel Voykin, CEO of NT Hydro.

Design work and projects that were collaborations with NWT businesses were the only ones that made real progress in 2019, according to Voykin.

The $62 million cut more than halves the NT Hydro’s budget for capital project, while the Northwest Territories Power Corporation’s capital budget is also being cut by $44.4 million, around 46 per cent.

There are several big projects which have been delayed, which are contributing to the cuts.

The Inuvik High Point Wind Project remains behind schedule and will continue to be throughout the upcoming year, according to Voykin. The delays come as a result of difficulties navigating the regulatory applications for the winter access road. The timeline for passing the regulatory process could be further pushed back as the road now faces a legal challenge, according to Voykin.

Around $19.5 million of work was planned for this upcoming fiscal year and only $3.8 million is now forecast to be completed.

The ransomware attack in April 2020 meant NT Hydro had to pushback start dates on a number of projects, resulting in $34 million in cuts to the capital budget work that had been planned for 2020-21.

Projects delayed by the ransomware attack include the Snare Forks G2 Overhaul, delaying $16 million of work, the L-150 transmission line re-anchoring project, delays totalling $5.5 million, the Snare Falls substation refurbishment, where $1.9 million in work was planned and the new Sachs Harbour power plant, delaying around $3 million in work.

Legal difficulties have also delayed the NTPC’s purchase of the Hay River power grid. The power corporation is appealing to the Supreme Court that an independent arbitrator set too high a value for the town’s power services.

Bailey Moreton
Bailey Moreton
Bailey is new to the north, arriving from Ottawa where he studied journalism at Carleton University. He has worked for newspapers in Halifax, Windsor, and Ottawa. He came to the north hoping to see polar bears. He will settle for a bison. If you have a tip, send it to 905 252-9781, or [email protected].

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Nahɂą Dehé Dene, Dehcho Education, GNWT to restore Charles Yohin School

The Nahɂą Dehé Dene Band, Dehcho Divisional Education Council, Nahanni Butte District Education Authority and the territorial government just announced that a new Charles Yohin School is in the works. A plan is in place to look at cost comparisons for either renovating the existing school or building a new one.

GNWT invests $400,000 in youth sports

The Government of the Northwest Territories has announced that they will be investing over $400,000 in youth sport and recreation through the Regional Youth Sporting Events Program.

Premier R.J. Simpson and Minister Caroline Wawzonek praise signing of MOU on Mackenzie Valley Highway

Premier R.J. Simpson and Minister Caroline Wawzonek spoke on the signing of a Memorandum of Understanding regarding the Mackenzie Valley Highway between Sahtu Secretariat Incorporated, the Gwich’in Tribal Council, and Pehdzéh Kı̨ First Nation yesterday.

GNWT updates medical travel benefits

The Government of the Northwest Territories is updating how medical travel benefits work for residents who have a valid NWT health care card, but do not have medical travel coverage through another program.  

Crews concerned about hot spots along Wood Buffalo Fire

The wildfire in Wood Buffalo near the Whooping Crane nesting area is currently estimated to be 53,000 hectares in size and remains out of control. Aircraft operations were halted today because of weather conditions and safety concerns