NT Hydro’s capital budget set to be cut by $62 million as projects delayed

The NT Hydro’s capital budget is set to be cut by more than $62 million, as delays have pushed completion on a number of major projects beyond 2021.

COVID-19, legal and regulatory delays and the ransomware attack in April 2020 — which prevented designers from accessing schematic drawings and getting plans approved — all caused project timelines to be pushed back, according to a letter sent to Infrastructure Minister Diane Archie by Noel Voykin, CEO of NT Hydro.

Design work and projects that were collaborations with NWT businesses were the only ones that made real progress in 2019, according to Voykin.

The $62 million cut more than halves the NT Hydro’s budget for capital project, while the Northwest Territories Power Corporation’s capital budget is also being cut by $44.4 million, around 46 per cent.

There are several big projects which have been delayed, which are contributing to the cuts.

The Inuvik High Point Wind Project remains behind schedule and will continue to be throughout the upcoming year, according to Voykin. The delays come as a result of difficulties navigating the regulatory applications for the winter access road. The timeline for passing the regulatory process could be further pushed back as the road now faces a legal challenge, according to Voykin.

Around $19.5 million of work was planned for this upcoming fiscal year and only $3.8 million is now forecast to be completed.

The ransomware attack in April 2020 meant NT Hydro had to pushback start dates on a number of projects, resulting in $34 million in cuts to the capital budget work that had been planned for 2020-21.

Projects delayed by the ransomware attack include the Snare Forks G2 Overhaul, delaying $16 million of work, the L-150 transmission line re-anchoring project, delays totalling $5.5 million, the Snare Falls substation refurbishment, where $1.9 million in work was planned and the new Sachs Harbour power plant, delaying around $3 million in work.

Legal difficulties have also delayed the NTPC’s purchase of the Hay River power grid. The power corporation is appealing to the Supreme Court that an independent arbitrator set too high a value for the town’s power services.

Bailey Moreton
Bailey Moreton
Bailey is new to the north, arriving from Ottawa where he studied journalism at Carleton University. He has worked for newspapers in Halifax, Windsor, and Ottawa. He came to the north hoping to see polar bears. He will settle for a bison. If you have a tip, send it to 905 252-9781, or [email protected].

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Series of “mock testing” using virtual tech to take place at Inuvik hospital

“We're expanding to have audio scopes and stethoscopes and we're looking at other tools that can be used. So that the virtual care out of Stanton or Inuvik can be provided into our smallest of communities. So a physician has always been available in those locations, via phone or travelling to them. But now we're offering a broader base. Connectivity has been resolved in part by using what's there, investing in new technology - so satellite connectivity,” said Dan Florizone

North braces for public service impact, where ‘small’ cuts run “deep”

"The impact on Northern and remote and Indigenous communities where we already know sometimes there is one position in the community, there is only a skeleton crew providing services can be felt definitely by Northerners who depend on certain services that are crucial to them," warns Josée-Anne Spirito, regional vice president at the Public Service Alliance of Canada.

Imperial Oil to end Norman Wells operations by summer 2026

Imperial Oil Ltd. will end production at its Norman Wells facility in the Northwest Territories in summer 2026.

Will LWBs guidelines bring awareness about water laws and compensation?

Gwich’in, Mackenzie Valley, Sahtu, and Wek’èezhìı Land and Water Boards – collectively, the LWBs have released a set of guidelines to raise awareness about the existence of water laws and the claims compensation process in the N.W.T. Despite the N.W.T. 's long history of mining, there have been few applications and leaders at the organization say a lack of awareness of the laws and lack of accessibility to the legal language of the water acts is part of the reason why.

Mackenzie Valley Hwy updates coming soon

“The sessions will provide an update on the Mackenzie Valley Highway Project, including an update on the environmental assessment process and timelines for regulatory milestones. Updates will also include planned engagement on multiple topics beginning in 2026 and ongoing through construction of the Project. Topics will include development of the Community Readiness Strategy, Corridor Working Group and Sub-Working Groups, and management plans for the Project,” said Lapointe.