NT Hydro’s capital budget set to be cut by $62 million as projects delayed

The NT Hydro’s capital budget is set to be cut by more than $62 million, as delays have pushed completion on a number of major projects beyond 2021.

COVID-19, legal and regulatory delays and the ransomware attack in April 2020 — which prevented designers from accessing schematic drawings and getting plans approved — all caused project timelines to be pushed back, according to a letter sent to Infrastructure Minister Diane Archie by Noel Voykin, CEO of NT Hydro.

Design work and projects that were collaborations with NWT businesses were the only ones that made real progress in 2019, according to Voykin.

The $62 million cut more than halves the NT Hydro’s budget for capital project, while the Northwest Territories Power Corporation’s capital budget is also being cut by $44.4 million, around 46 per cent.

There are several big projects which have been delayed, which are contributing to the cuts.

The Inuvik High Point Wind Project remains behind schedule and will continue to be throughout the upcoming year, according to Voykin. The delays come as a result of difficulties navigating the regulatory applications for the winter access road. The timeline for passing the regulatory process could be further pushed back as the road now faces a legal challenge, according to Voykin.

Around $19.5 million of work was planned for this upcoming fiscal year and only $3.8 million is now forecast to be completed.

The ransomware attack in April 2020 meant NT Hydro had to pushback start dates on a number of projects, resulting in $34 million in cuts to the capital budget work that had been planned for 2020-21.

Projects delayed by the ransomware attack include the Snare Forks G2 Overhaul, delaying $16 million of work, the L-150 transmission line re-anchoring project, delays totalling $5.5 million, the Snare Falls substation refurbishment, where $1.9 million in work was planned and the new Sachs Harbour power plant, delaying around $3 million in work.

Legal difficulties have also delayed the NTPC’s purchase of the Hay River power grid. The power corporation is appealing to the Supreme Court that an independent arbitrator set too high a value for the town’s power services.

Bailey Moreton
Bailey Moreton
Bailey is new to the north, arriving from Ottawa where he studied journalism at Carleton University. He has worked for newspapers in Halifax, Windsor, and Ottawa. He came to the north hoping to see polar bears. He will settle for a bison. If you have a tip, send it to 905 252-9781, or [email protected].

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Yellowknife police announce Bike Bait program to deter bike theft

Yellowknife RCMP has announced they will be launching a ‘Bike Bait’ program to help prevent bicycle theft this summer.

Wildfire prevention to continue across southern NWT in coming weeks

Wildfire prevention activities are taking place in southern regions of the territory this week. Crews are working on tree line remediation and wildfire prevention in Hay River, while Fort Smith saw a prescribed burn Wednesday. Today, territorial officials plan to announce a new wildfire prevention program.

Skills Canada NWT announces list of competitors for national competition

Skills Canada NWT has announced Team NWT, 19 competitors from the territory who will be travelling to compete in the Skills Canada National Competition next week.  

Early Childhood Infrastructure Fund split into separate funding streams

The Government of the Northwest Territories has announced that the Early Childhood Infrastructure Fund will now be split into three distinct funding streams.

Ministers congratulate new Major Project Review Tool

Ministers Jay Macdonald, Caitlin Cleveland, and Caroline Wawzonek have released a statement following the launch of the Mackenzie Valley Environmental Impact Review Board’s new Regional Database and Major Project Review Tool last week.