NT Hydro’s capital budget set to be cut by $62 million as projects delayed

The NT Hydro’s capital budget is set to be cut by more than $62 million, as delays have pushed completion on a number of major projects beyond 2021.

COVID-19, legal and regulatory delays and the ransomware attack in April 2020 — which prevented designers from accessing schematic drawings and getting plans approved — all caused project timelines to be pushed back, according to a letter sent to Infrastructure Minister Diane Archie by Noel Voykin, CEO of NT Hydro.

Design work and projects that were collaborations with NWT businesses were the only ones that made real progress in 2019, according to Voykin.

The $62 million cut more than halves the NT Hydro’s budget for capital project, while the Northwest Territories Power Corporation’s capital budget is also being cut by $44.4 million, around 46 per cent.

There are several big projects which have been delayed, which are contributing to the cuts.

The Inuvik High Point Wind Project remains behind schedule and will continue to be throughout the upcoming year, according to Voykin. The delays come as a result of difficulties navigating the regulatory applications for the winter access road. The timeline for passing the regulatory process could be further pushed back as the road now faces a legal challenge, according to Voykin.

Around $19.5 million of work was planned for this upcoming fiscal year and only $3.8 million is now forecast to be completed.

The ransomware attack in April 2020 meant NT Hydro had to pushback start dates on a number of projects, resulting in $34 million in cuts to the capital budget work that had been planned for 2020-21.

Projects delayed by the ransomware attack include the Snare Forks G2 Overhaul, delaying $16 million of work, the L-150 transmission line re-anchoring project, delays totalling $5.5 million, the Snare Falls substation refurbishment, where $1.9 million in work was planned and the new Sachs Harbour power plant, delaying around $3 million in work.

Legal difficulties have also delayed the NTPC’s purchase of the Hay River power grid. The power corporation is appealing to the Supreme Court that an independent arbitrator set too high a value for the town’s power services.

Bailey Moreton
Bailey Moreton
Bailey is new to the north, arriving from Ottawa where he studied journalism at Carleton University. He has worked for newspapers in Halifax, Windsor, and Ottawa. He came to the north hoping to see polar bears. He will settle for a bison. If you have a tip, send it to 905 252-9781, or [email protected].

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

GNWT will not administer assault-style firearm buyback program

The GNWT has announced that the federal government will be taking responsibility for administering the federal Assault-Style Firearms Compensation Program in the territory, while the territorial government will focus on community safety and effective policing.  

Chair Erwin Elias wins election as new leader of Inuvialuit Regional Corporation

Newly elect Chair Erwin Elias has stepped into his new leadership role at Inuvialuit Regional Corporation after winning the election yesterday. The election was held yesterday at the Midnight Sun Complex in Inuvik. Leaders across the territory are congratulating Chair Elias on the win, including Premier R.J. Simpson who issued a statement this morning wishing the leader success in the role.

Indigenous North transforming health care ‘system’ at YK Summit

A Summit is bringing together Indigenous leaders and health leaders beyond discussions, to new grounds that some say could transform the current health care system.   The NWT Council of Leaders and representatives from the GNWT are hosting the event, titled Following the North Star: Primary Health Care Reimagined Together.

RCMP investigate suspicious fire in Yellowknife

Yellowknife RCMP are investigating a suspicious fire that occurred in the early morning of January 20th

Yellowknife begins phase 2 of lead testing

The City of Yellowknife has begun Phase 2 of water testing in municipal buildings. The tests were begun because of elevated levels of lead reported in water at local schools. The first phase of testing detected dangerous levels of lead in 4 of the tested buildings.