NT Hydro’s capital budget set to be cut by $62 million as projects delayed

The NT Hydro’s capital budget is set to be cut by more than $62 million, as delays have pushed completion on a number of major projects beyond 2021.

COVID-19, legal and regulatory delays and the ransomware attack in April 2020 — which prevented designers from accessing schematic drawings and getting plans approved — all caused project timelines to be pushed back, according to a letter sent to Infrastructure Minister Diane Archie by Noel Voykin, CEO of NT Hydro.

Design work and projects that were collaborations with NWT businesses were the only ones that made real progress in 2019, according to Voykin.

The $62 million cut more than halves the NT Hydro’s budget for capital project, while the Northwest Territories Power Corporation’s capital budget is also being cut by $44.4 million, around 46 per cent.

There are several big projects which have been delayed, which are contributing to the cuts.

The Inuvik High Point Wind Project remains behind schedule and will continue to be throughout the upcoming year, according to Voykin. The delays come as a result of difficulties navigating the regulatory applications for the winter access road. The timeline for passing the regulatory process could be further pushed back as the road now faces a legal challenge, according to Voykin.

Around $19.5 million of work was planned for this upcoming fiscal year and only $3.8 million is now forecast to be completed.

The ransomware attack in April 2020 meant NT Hydro had to pushback start dates on a number of projects, resulting in $34 million in cuts to the capital budget work that had been planned for 2020-21.

Projects delayed by the ransomware attack include the Snare Forks G2 Overhaul, delaying $16 million of work, the L-150 transmission line re-anchoring project, delays totalling $5.5 million, the Snare Falls substation refurbishment, where $1.9 million in work was planned and the new Sachs Harbour power plant, delaying around $3 million in work.

Legal difficulties have also delayed the NTPC’s purchase of the Hay River power grid. The power corporation is appealing to the Supreme Court that an independent arbitrator set too high a value for the town’s power services.

Bailey Moreton
Bailey Moreton
Bailey is new to the north, arriving from Ottawa where he studied journalism at Carleton University. He has worked for newspapers in Halifax, Windsor, and Ottawa. He came to the north hoping to see polar bears. He will settle for a bison. If you have a tip, send it to 905 252-9781, or [email protected].

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Pit filling begins at Diavik Diamond Mine

Rio Tinto has announced that they have taken a significant step towards reclamation at the Diavik Diamond Mine, having begun filling the pits with water from Lac de Gras.

Fort Smith police charge suspect with assaulting an officer

Fort Smith RCMP have charged a suspect in relation to several incidents, including the assault of several police officers.

GNWT releases technical report on cancer in the NWT

The Government of the Northwest Territories has released their technical report on occurrences of cancer in the territory from 2011 to 2022, giving an overview of territorial trends over that 11-year span.

Extreme fires more than twice as likely in the NWT due to climate change according to new study

Imperial College London’s World Weather Attribution has released a report on their findings regarding the effects of human-caused climate change on wildfires, finding that fossil fuel-driven climate change has caused extreme fire conditions in the NWT to be more than twice as likely to occur.

Improvements to supports for commercial fishers announced

Improvements to the Commercial Fishery Support Program and a new accreditation for the Hay River fish plant are hoping to help support and renew momentum for the NWT’s commercial fishing industry.