Giant Mine drilling program underway on Yellowknife Bay

Winter drilling on the Yellowknife Bay area of Great Slave Lake has begun as part of the Giant Mine Remediation Project.

Flooding to strengthen the ice started on February 9th and is expected to take place over three weeks. Drilling is then expected to start in March and is also expected to take three weeks.

The drilling will provide the project team information about the lake bed’s ability to bear weight for a proposed tailings cover. Officials will also be using the drilling data to help design an outfall location for the new water treatment plant.

The drilling will be happening at three locations; the Yellowknife Bay area of the lake by the Great Slave Sailing Club, the Giant Mine boat launch, and approximately 1 km north along the shoreline from the boat launch.

As the program moves along the shoreline, areas that were drilled and have safely frozen over will be made available to the public.

People in the area are being asked to respect safety signage and keep a safe distance from active work areas.

Active remediation is expected to take approximately 10 years, after which the site will move into long-term monitoring and ongoing care and maintenance.

Keven Dow
Keven Dow
News. Keven moved here from Ontario in November of 2018. As of December Keven is back to doing full-time news after transitioning into a news/mid-days position in late 2019. Prior to that, he was doing weekends/news for about 8-9 months. He's from a small tomato town in Ontario and went to College at Fanshawe for Radio Broadcasting. He loves talking about sports, entertainment, the community, and local events. Got a news tip? Email me at [email protected]

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Dettah Ice Road closed for the season

The Northwest Territories department of Infrastructure has just closed the Dettah Ice Road for the season.

Feds pledge $4B for housing in Indigenous Northern, remote communities

The federal government says they are committing $4-billion for Indigenous housing in urban, rural and northern communities. The announcement was made in Behchokǫ̀ on Friday. The multi billion dollar plan, dubbed the Urban, Rural and Northern Indigenous Housing Strategy, intends to balance Indigenous-led funding agreements and open, project-based funding for Indigenous housing projects.

NorthWords NWT releases schedule and author list for 2026 festival

NorthWords NWT has released the schedule and visiting authors for their 2026 Writer’s Festival.

Alberta bill would end seasonal clock changes

Alberta has taken the first step toward ending seasonal clock changes.

NWT’s spring flow: some of thickest ice on lowest water on record

Scientists with GNWT’s Environment and Climate Change centre say water levels are low across most of the territory but above-average snowpack in the Slave and Liard river basins, combined with a delayed spring melt, could result in near-normal spring flows. Scientists advised weather in the weeks ahead will plays a key role in the possibility of flooding.