Units at new Stanton Hospital to feature ‘significant’ upgrades

The Stanton Hospital Renewal Project is on schedule, according to government officials and developers.

The Government of the Northwest Territories (GNWT) held a technical briefing to provide an update on the project Thursday. Members of the public were also invited to an open house in the evening.

Construction on the new hospital began in October 2015 immediately adjacent to the existing hospital in Yellowknife. Officials still expect the build should be complete in December 2018.

Also: Images: Take A Closer Look At Yellowknife’s New Hospital

Remediation and redevelopment of the current hospital will follow the transition to the new facility.

“One of the big advantages of a new build approach compared to possibly a renovation approach is the phasing,” said Mike Burns, assistant deputy minister of public works and services.

“We’re going to have a single construction period delivered by a single contractor which means we’re going to have minimal interruption to the existing operations at the hospital today.

“There will be a period of transition after the construction is completed. But it will be fairly minimal compared to a renovation project.”

Construction of the new building is expected to cost $350 million. The project is being funded using a public-private partnership, or P3 model.

The territorial government will also provide $18 million a year for 30 years to Boreal Health Partnership (BHP) for operation and maintenance of the facility – representing a total commitment of $750 million from the GNWT.

What can patients expect from the new hospital?

The new hospital will be twice as big as the existing one, going from 13,300 m² to 27,500 m².

Designers say they have made accessibility and comfort a priority.

To that end, the new hospital’s emergency department will be situated towards the front of the building instead of around back.

UNTITLED3

The main entrance will also be on grade so patients with mobility issues won’t have to worry about accessibility.

“The new Stanton is going to be a state-of-the-art facility,” said Jeannie Dhaliwal, director of redevelopment with the Stanton Hospital Renewal Project.

Dhaliwal says patients can expect to have a clear view of Frame Lake from their rooms, almost double the current parking space and access to a therapeutic garden.

There will also be significant enhancements to the hospital’s emergency department, psychiatric unit (including an outdoor patio), medicine unit and infection control.

Meanwhile, double occupancy units will become single patient rooms and the number of surgery beds will increase from 10 to 26.

Because the new hospital is expected to have a 30-year lifetime, developers say its larger blueprint is designed to handle an increase in volume.

UNTITLED4

So, what does that mean for staffing levels once staff transition from the current hospital to the new one?

“We’re intending to go into the new building with the same staffing model,” said Sue Cullen, CEO of the Stanton Territorial Health Authority.

“The building is built until 2045 so we anticipate an increase.

“The thought was that we’d go in with our existing staffing model and as the occupancy changes, so would the staffing model.”

Cullen says that should allow them to have flexibility during a period of transition.

Stanton officials are also exploring the feasibility of a magnetic resonance imaging (MRI) unit. At present, patients requiring that care are sent south.

In 2012, a cost-benefit analysis determined that it was cheaper to send patients to Edmonton for tests than it was to buy and operate a machine in the territory.

Cullen says officials are in the process of determining if that’s still the case.

So, what happens to the old hospital?

Once the transition to the new hospital is complete, BHP will be responsible for stripping back the existing building to the shell and clearing it of any hazardous materials.

Burns says conditions provide that the building can’t be demolished or mothballed in the next 30 years.

Beyond remediation and redevelopment, risk is born by the commercial developer, Ventura Stanton Incorporated, for the life of the 30-year revenue lease agreement.

However, the GNWT will retain ownership of the hospital and associated land, including parking.

Following Thursday’s technical briefing, officials provided reporters with a tour of mock-up designs located in the upper level of Centre Ice Plaza.

Patrick Cannon, left, Mike Burns, Sandy Kalgutkar, Jeannie Dhaliwal and Sue Cullen led Thursday's technical briefing.
Pat Cannon, left, Mike Burns, Sandy Kalgutkar, Jeannie Dhaliwal and Sue Cullen led Thursday’s briefing.
Jeannie Dhaliwal walked reporters through a series of mock-up designs Thursday.
Jeannie Dhaliwal walked reporters through a series of mock-up designs Thursday.
A mock-up design of a single patient room.
A mock-up design of a single patient room.
Power outlets featured in one of the mock-up units.
Power outlets featured in one of the mock-up units.
Mike Gibbins
Mike Gibbins
Hello and thank you for listening to 100.1 Moose FM! To contact me, you can email me, find me on Twitter or call (867) 920-4663.

Continue Reading

You may also like



cjcd Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

GNWT providing water support after lead found in 5th YK1 school in Nov.

The GNWT announced that after a fifth YKI school tested positive for elevated lead levels on Nov. 26, schools across the territory awaiting testing or results will now be able to access alternative drinking water as a precaution.

Vigil being held to remember those affected by gender-based violence

The Status of Women Council of the NWT and YWCA NWT are holding a public vigil on the National Day of Remembrance and Action to acknowledge and remember those who have been affected by gender-based violence. Hawa Dumbuya-Sesay, Executive Director of the YWCA NWT says communities continue to be deeply impacted by intimate partner violence, femicide, and the crisis of Missing and Murdered Indigenous Women and Girls.

Northern planning firm launches student scholarship

“Locally grown planners deeply understand their communities and are uniquely equipped to engage community members in achieving the future they envision,” says Wenman. Planit North's scholarship is geared towards youth with a focus on Northern Indigenous students.

Housing NWT to take over operations of 2 YK shelters

Next year, Housing NWT will take over operations of two Yellowknife shelters including the Sobering Centre and the Yellowknife Day Shelter. Currently, the facilities are being managed by the health and social services authority. Housing NWT currently oversees shelter services in other regions of the NWT. According to an announcement released by the GNWT, the change is part of a move towards a “more coordinated” approach to homelessness across the territory.

YK homeowners can expect a tax increase of 3.67 per cent in 2026

City of Yellowknife homeowners can expect a tax increase of 3.67 per cent next year, about half of what was originally estimated in budget talks last month. The original 7 per cent estimate was reduced following a number of developments, including council ditching plans on a few proposed expenditures and adding into the mix carbon tax monies flowing in for 2026